Since the beginning of the year, specialists of the Orenburgenergo branch of Rosseti Volga (a brand of IDGC of Volga, PJSC) have connected 499 new facilities with a total capacity of 53 megawatts to the electric grids. Power engineers included residential buildings, agricultural and industrial sites, trade pavilions and broadcasting network equipment in the grid.
Among the connected facilities is the Orenburg SES-4 solar power station with a capacity of 15 MW in the Novosergievsky district. To include SES in the power grid, power engineers reconstructed four substations in the west of the region. At the substations of Novosergievskaya, Lapaz, Zarechnaya and Tashlinskaya, additional relays were installed and current transformers were set up. Work carried out by the Orenburgenergo specialists on the technological connection of the solar station contributed to the development of green energy.
“Technological connection is one of the main activities of the Orenburgenergo branch. This procedure is available and carried out in several steps and strictly by law. All deadlines are clearly observed from the filing of the application to the actual connection of the facility to the electric network,” Viktor Zilberstein, Deputy Director of the branch for the sale and development of services, emphasizes.
Despite the current epidemiological situation, the energy companies of Rosseti Volga continue to provide technological connection services on time. You can place an application remotely through your personal account on the Rosseti Volga company website (www.mrsk-volgi.ru). In the same place, online, you can track its progress and conclude an agreement with a power company without visits to the office. All documents are signed by electronic signature. You can also apply for technological connection on the Unified portal of electric grid services ïîðòàë-òï.ðôor using the Rosseti – Personal Account application (Android and iOS).
|