According to the planned schedule, the repair program of the Mordovenergo branch of Rosseti Volga (a brand of IDGC of Volga PJSC) is being implemented. The work is carried out as part of the execution of the order of the General Director of Rosseti, PJSC Pavel Livinsky on the full and timely implementation of a package of measures to ensure reliable and high-quality power supply to consumers in the coming winter.
By the end of May, the repair of 12 substations will be completed: 110 kV Bolshoy Azyas substation, 110 kV GKS substation, 110 kV Dubenki substation, 110 kV Penzyatka substation, 110 kV Purdoshki substation, 110 kV Pyatina substation, 110 kV Sabaevo substation, 110 kV Smolnaya substation, 110 kV Temnikov substation, 110 kV Troitsk substation, 110 kV Erzya substation, 35 kV Dachnaya substation. 97 transformer substations of 10/0.4 kV and 5 power transformers of 10/0.4 kV will also be repaired. In addition, this month in the settlements of the republic, Mordovenergo personnel will replace 2.9 km of uninsulated 0.4 kV overhead lines with a self-supporting insulated wire, which significantly reduces the possibility of emergency shutdowns.
This month, clearing of overhead power lines continues. Work is planned on an area of almost 84 hectares.
Power engineers carry out work under tight control of compliance with security measures in the current epidemiological situation. The staff is fully provided with personal protective equipment and hygiene. Constant monitoring of the health status of employees is ongoing.
|