In January-March 2022 electricity output of TGC-1, including JSC
Murmanskaya CHPP, comprised 9,376.9 million kWh, up by 2.3%
year-on-year.
TGC-1 CHPPs production in 1Q 2021 grew by 4.9% on
the back of growing demand for electricity in the North-West.
Comparable HPPs output decreased by 2.5% vs. high water factor in 1Q
2021.
TGC-1 electricity output summary (million kWh)
|
3Ì 2021
|
3Ì 2022
|
Change
|
Nevsky branch
|
6,192.9
|
6,405.0
|
+3.4%
|
Karelsky branch
|
1,095.5
|
1,008.6
|
-7.9%
|
Kolsky branch
|
1,873.3
|
1,955.7
|
+4.4%
|
TGC-1 total
|
9,161.7
|
9,369.3
|
+2.3%
|
JSC Murmanskaya CHPP
|
7.55
|
7.58
|
+0.4%
|
TGC-1 total, including JSC Murmanskaya CHPP
|
9,169.3
|
9,376.9
|
+2.3%
|
The volume of heat output from collectors of
TGC-1, including JSC Murmanskaya CHPP, comprised 9,689.8 thousand
Gcal, which is 8.5% lower than for 3M 2021 due to higher ambient
temperatures in the reporting period.
TGC-1 heat output summary (thousand Gcal)
|
3Ì 2021
|
3Ì 2022
|
Change
|
Nevsky branch
|
8,437.0
|
7,735.7
|
-8.3%
|
Karelsky branch
|
771.7
|
691.6
|
-10.4%
|
Kolsky branch
|
568.9
|
519.0
|
-8.8%
|
TGC-1 total
|
9,777.6
|
8,946.3
|
-8.5%
|
JSC Murmanskaya CHPP
|
813.2
|
743.6
|
-8.5%
|
TGC-1 total, including JSC Murmanskaya CHPP
|
10,590.8
|
9,689.8
|
-8.5%
|
For more information about the results of the
company’s production performance, please visit the Reports section
of the corporate website.
About
TGC-1 (part of the Gazprom Energoholding
Group) is a leading producer and supplier of electricity and heat in
the North-West of Russia. TGC-1 comprises 52 power plants within four
constituent entities of the Russian Federation: St. Petersburg, the
Republic of Karelia, and Leningrad and Murmansk Oblasts.
TGC-1 installed electric capacity of the Company’s
stations amounts to 6.9 GW and heating capacity of 13.5 thous.
Gcal/hr. Major shareholders are Gazprom Energoholding LLC
(51.79%) and Fortum Power and Heat Oy (29.45%).
|