For 2007 capital and average repairs of 26 units, including 16 power coppers which evaporation is 2783 t/hour, 8 turbines by capacity 306 MVA, two water-heating coppers productivity 200 Gkal/hour were planned. It is planned to replace 1,5 km of thermal networks in Ekaterinburg (in one-trumpet calculation).
On the end of August the repair of power objects is conducted according to the established schedule. Capital and average repairs of 10 power coppers, 5 turbines, 2 water-heating coppers are executed. 1,4 km of pipelines of thermal networks were laid, the part from them was replaced by the pipes preliminary isolated polyurethane resin. Hydraulic tests of the thermal networks were finished, the revealed defects were eliminated.
Plans on a fuel bookmark for the forthcoming autumn-winter period were executed. Coal stocks on power stations and boiler-houses ?GC-9 in Sverdlovsk area made 506 thousand tons at the provided 365 thousand, black oil - 62 thousand tons, that on 13 thousand tons more than planned.
According to target dates there is a preparation of industrial buildings, repair and replacement of roofs, inspection and repair of chimneys.
Tilthe 15-th ofl September, power men of the company spend joint preemergency trainings with participation of operation personnel of stations, thermal networks and municipal services of cities of Sverdlovsk area.
Industrial branches TGC-9 in Sverdlovsk area will be prepared for the autumn-winter maximum, provided a reliable and uninterrupted heat supply of consumers during the heating period.
|