Today JSC "Territorial Generation Company N2" (TGC-2) has received the passports of readiness to work during the autumn-winter period 2006/07. The special commission appointed by the order of RAO "UES of Russia" signs the certificate of readiness. After its signing chairman of the commission, the head of department of technical audit and industrial inspection of BE-1 of RAO "UES of Russia" Andrey Krivoguzov has solemnly handed the passport of readiness of JSC "TGC-2" to work in autumn-winter period 2006/07 over General Director of the Company Andrey Vagner.
Feature of present repair campaign became transition to new organizational - administrative system of preparation enterprises to work in autumn-winter conditions. This technology includes the traditional approach to planning and realizations of actions to forthcoming autumn-winter period, and also formation of base for qualitative preparation for two subsequent autumn-winter periods. Transition to a three-year cycle of preparation is caused by requirements of maintenance of reliability of work energy enterprises after failure in the Moscow power supply system in May of the last year and experience of passage of the period of extremely low temperatures in previous autumn-winter period 2005/06.
The total cost of repair campaign is 717,5 million roubles. At enterprises of TGK-2 have been carried out operating repairs of 56 turbines, 81 power boiler, 30 water-heating boilers; capital and average repairs of 7 turbines, 18 boilers; 29 kms of the main and distributive pipelines of thermal networks are replaced.
During preparation to autumn-winter period on power stations and boiler-houses has been carried out an approbation boilers on reserve fuel.
Another feature of present repair campaign is preparation for winter transferred TGC-2 in rent of municipal boiler and thermal networks in Arkhangelsk, Konakovo, Vishni Volochok and Tver also. TGC-2 has prepared for a cold season 59 municipal boiler-houses and more than 400 kms of thermal networks. The Company has allotted more than 60 million roubles on these purposes.
The information.
JSC "Territorial generation company #2" was registered on 19 April 2005 in the city of Yaroslavl. The resolution to establish JSC "TGC-2" as a wholly-owned subsidiary of RAO "UES of Russia" was approved by the Board of Directors of RAO "UES of Russia" on 25 February 2005.
TGC-2 includes the generating enterprises of six regions - the Arkhangelsk, Vologda, Kostroma, Novgorod, Tver and Yaroslavl areas. Under control of the company there are 16 thermal power stations, 8 boiler-houses, 4 enterprises of thermal networks. The installed general electric wattage of enterprises of TGK-2 - 2423,5 mWt, the installed thermal wattage - 12156 Gkal/hour.
Besides the Company rents municipal and departmental boiler-houses in Arkhangelsk, Severodvinsk, Tver, Konakovo and Vishny Volochok. There are also JSC "Arkhangelsk retail company", JSC "Kostroma Retail Company" and JSC "Tver energy Retail Company" in asset management of TGC-2.
Authorized Capital of TGC-2 is 7 billion 117 million 127 thousand 045 roubles and 01 copeck now. The share of RAO "UES of Russia" in Authorized Capital of TGC-2 is 49,18 % from total of shares.
|