RusHydro Group announces its operating results for 1Q 2021

April 20, 2021. Moscow, Russia. PJSC RusHydro (ticker symbol: MICEX-RTS, LSE: HYDR; OTCQX: RSHYY) announces operating results for the 1st quarter of 2021, of the parent company and subsidiaries of RusHydro Group reflected in consolidated financial statements.

Key highlights:

  • Stable production results at the long-run average level.  Decrease of output year on year on the back of high base effect of 2020 driven by extremely high water inflows to the main of reservoirs of the HPPs of the Volga-Kama cascade (x1.5-6.4 the normal level);

  • 28,496 GWh - total electricity generation by RusHydro Group excluding Boguchanskaya hydropower plant in 1Q 2021 (-13.2%) 1;

  • 19,950 GWh - electricity output from hydro and pumped storage plants in 1Q 2021 excl. Boguchanskaya HPP(-19.5%);

  • 8,436 GWh – electricity output from thermal power plants (+6.0%).

  • 12,980 thousand Gcal/h – heat output from thermal power plants in the Far Eastern Federal District (+7.1%).

  • 12,467 GWh – sales by Group’s electricity retail companies in 1Q 2021 (+4.4% y-o-y).

Electricity generation by the plants of RusHydro Group, GWh



 

1Q'21

1Q'20

chg, %

1Q'19

chg, %

Center of Russia

7,910

12,373

-36.1%

8,183

-3.3%

South of Russia and North Caucasus

1,185

1,269

-6.6%

1,169

1.4%

Siberia

5,722

6,047

-5.4%

5,642

1.4%

Total for the price zones

14,817

19,688

-24.7%

14,994

-1.1%

Far East

4,314

4,368

-1.2%

3,178

35.8%

RAO ES East

9,366

8,787

6.6%

9,171

2.1%

TOTAL

28,496

32,843

-13.2%

27,342

4.2%

incl. by HPPs, PSPPs 2

19,950

24,768

-19.5%

19,100

4.5%

incl. by TPPs and other

8,436

7,958

5.1%

8,135

2.8%

Incl. by alt. renewables (geothermal, solar, wind)

110

116

-5.6%

107

2.5%

Boguchanskaya HPP 3

5,087

4,636

9.7%

3,741

36.0%

 

The underlying factors of the production change in January-March 2021 were:

  • water inflows to the reservoirs of the Volga-Kama cascade, Siberia and the Far East at the normal level or slightly above, yet below last year’s level;

  • water inflows to the  reservoir of Chirkeyskaya HPP at the normal level;

  • increase of electricity consumption in the Far East by 6.1%

  • increase of heat output in the Far East driven by weather conditions.

Center of Russia

Total water inflow to the reservoirs of the Volga-Kama cascade reached 24.4 km3 (normal level - 23.5 km3), in April water inflow is expected at 47-67 km3 (normal level - 65.9 km3).

South of Russia and North Caucasus

Water inflow to Chirkeyskaya HPP on the Sulak River was close to the normal level. In April 2020 according to Hydrometeorology Center of Russia total water inflow is expected at the normal level as well.

Siberia

Water inflows to Sayano-Shushenskoye reservoir in the first quarter of 2021 was 1.4x above the normal level. In April 2021, water inflows to Sayano-Shushenskoye and Novosibirskoye reservoirs are expected 30-85% above the normal level. 

Far East

In 1Q 2021 water inflows to Zeyskoye reservoir was 2.7x the normal level, while inflows to Kolymskoe reservoir were 30% above the normal level. In April, water inflows to Kolymskoye reservoir are expected at the normal level, to Zeyskoye reservoir – above the normal level.

Total electricity generated by RAO ES East subgroup in the first quarter of 2021 amounted to 9,366 GWh, an increase of 6.6% as compared to the first quarter last year.

The main driver behind the production increase was growth of electricity consumption in the region by 6.1% to 8,235 GWh.

Heat output by thermal plants of RAO ES East Subgroup in the first quarter of 2021 increased by 7.1% to 12,980 GCal as compared to the corresponding period of 2020 due to lower air temperatures in the regions of presence of JSC DGK, PJSC Yakutskenergo and JSC Chukotenergo.

Heat output by thermal plants of RAO ES of the East Subgroup, ‘000 GCal



 

1Q'21

1Q'20

Chg.

JSC DGK incl.

8,893

8,219

8.2%

   Primorye power system

1,840

1,676

9.8%

   Khabarovsk power system

5,068

4,799

5.6%

   Amur power system

1,101

981

12.2%

   South Yakutsk power district

885

763

15.9%

JSC RAO ES East (CHPP Vostochnaya)

366

353

3.5%

PJSC Yakutskenergo

1,166

1,068

9.1%

UES of East

10,424

9,641

8.1%

Yakutsk power system incl.

606

515

17.6%

   JSC Sakhaenergo

28

29

-3.9%

   JSC Teploenergoservice

578

487

18.9%

Kamchatka power system incl.

751

761

-1.3%

   PJSC Kamchatskenergo

719

731

-1.6%

   JSC KSEN

32

30

4.6%

Magadan power system

493

474

4.0%

Chukotka AO power system

148

160

-7.7%

Sakhalin power system

558

570

-2.1%

Isolated power systems

2,556

2,481

3.0%

TOTAL

12,980

12,246

7.1%

 

Electricity retail

Total electricity output by RusHydro Group’s energy retail companies in 1Q 2021 increased by 4.2% to 15,044 GWh as compared to 1Q 2020. The increase came on the back of climate factor as the average temperature in the first quarter of 2021 was below that of the first quarter of 2020.

Total electricity output by RusHydro’s companies located in the isolated energy systems in the Far East Federal District amounted to 2,577 GWh in 1Q 2021, an increase of 3.4% as compared to the same period last year.

Electricity output by RusHydro Group’s retail companies, GWh



 

1Q’21

1Q’20

chg, %

PJSC Krasnoyarskenergosbyt

3,552

3,342

6.3%

JSC Chuvash retail company

981

911

7.7%

PJSC Ryazan retail company

683

648

5.4%

JSC ESC RusHydro

362

471

-23.2%

PJSC DEK

6,888

6,575

4.8%

Total

12,467

11,947

4.4%

Isolated energy systems (for reference)

2,577

2,491

3.4%

Total by Group

15,044

14,438

4.2%

 

Water inflows forecast

According to the forecast of the Hydrometeorology Center of Russia, the following dynamics of water inflows to the major reservoirs is expected in the 2nd quarter of 2021:

  • Total water inflows to reservoirs of the hydropower plants Siberia, Chirkeyskoye reservoir and Volga-Kama cascade are expected at the normal level;

  • In the Far East, inflows to Zeyskoye reservoir are expected to be at the long-run average, to Kolymskoye reservoir – below the normal level.

1 Hereinafter data is reported excluding Armenia and Primorskaya GRES. On 11.03.2020 RusHydro has finalized divestment of its assets in Armenia to PJSC Hrazdan Power Company (HrazTES, Tashir Group). Primorksaya GRES was sold to SUEK Group in June 2020

2 Includes generation by HPPs of JSC RusHydro, Kolymskaya HPP and Viluiskie HPPs (RAO ES East Subgroup).

3 The Boguchanskaya hydropower plant is part of the Boguchanskiy Energy and Metals Complex (BEMO), a 50/50 joint venture (JV) between RusHydro and UC RUSAL, and is not part of RusHydro Group. According to RusHydro’s shareholding in the JV (50%), the results of the plant are reported in the official financial statements in “Share of results of associates and jointly controlled entities”. Operations of the HPP have been put into the press-release for general reference.






Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z



Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer