In 2017 Branch of IDGC of Volga, PJSC (member of Rosseti Group) – Penzaenergo – received 2366 applications of consumers for technological connection to power grids. The quantity of capacity declared by individuals and legal entities amounted to 121 MW. Besides, in the same period, 2027 technological connection agreements with total committed capacity of 39.3 MW were executed.
In 2017 Penzaenergo Branch completed 2209 technological connections of consumers’ – individuals and legal entities – facilities with total capacity of 39.2 MW. Within the obligations performed by Penza Branch of IDGC of Volga under technological connection agreements, 79.8 km were built, and 4.25 km of 6-10/0.4 kV distribution grids were reconstructed. Besides, power engineers increased capacity of its substation equipment by 4.54 MVA. T
he largest facilities among connected to grids of Penzaenergo Branch were the following: production facilities in Penza (1.1 MW), hatching house in Golitsino village (0.9 MW), reclamation complex and production facility within the borders of Olenevskiy rural council of Penzenskiy district (0.88 MW), horticultural societies “Dubrava-3” and “Astra” (0.8 MW), candy manufacturing in town of Belinskiy (0.6 MW), housing community in Malaya Valyaevka village, wholesale warehouse, sausage department, etc.
|