Penzaenergo branch of IDGC of Volga, JSC is getting prepared for the summer repairs campaign.
Penza powermen plan to repair 270 transformer 35-110 kilovolt substations, 989 km of OL -35-110 kilovolt and 2,740 km of OL 0.4-10 kilovolt. The capital repairs of 8 grid transformers, 311 circuit breakers, and 570 disconnectors will be made. Repair crews will change over 2,000 supports and 857 attachments. 439 hectare of the breakthrough will be also cleared and 439 pcs. of chains of insulators will be repaired.
Penzaenergo, JSC will assign RUR 108.4 million for the summer repairs program.
Just for the comparison: RUR 90 million were assigned for these goals in 2007.
|