The Central production department of Saratov distribution grids of IDGC of Volga, JSC has begun to install indoor switchgear at substation “Novosokolovogorskaya” in Volga region of Saratov city.
The switchgear installation will make it possible to load the transformer at a full capacity which was installed the last year, the capacity of which amounts to 25 megavolt-amperes and to provide power supply of the existing and would-be consumers. The technical characteristics of the equipment being launched make it possible to connect 25 thousand flats. It’s vitally necessary in the region where intensive construction works are performed.
The equipment being installed is produced at a new technological base, controlled by the microprocessor technology, is more saving, reliable and has a long life. Its installation is planned for April and May – to implement the commissioning. In June, “Novosokolovogorskaya” substation may start connection of new consumers who have already started sending applications.
The installation of one more transformer with the capacity of 10 megavolt-amperes is planned at substation “Novosokolovogorskaya this year. It will help to reserve the power supply of Sokolovogorsky township.
|