May 30, 2011 |
Rosseti North-West |
|
In 2011, IDGC North-West plans to procure goods, works and services for 16.8 billion rubles |
|
May 27, 2011 |
Rosseti North-West |
|
Top managers “IDGC North-West” answered the questions of investors |
|
May 26, 2011 |
Rosseti North-West |
|
“IDGC Northwest” begins installation of equipment at the substation 110/35/10 kV “Antushevo" located in Vologda Region |
|
May 25, 2011 |
Rosseti North-West |
|
IDGC Northwest starts the next step in the implementation of major investment projects in Vologda region |
|
May 24, 2011 |
Rosseti North-West |
|
Governor of republic of Karelia and General director IDGC Northwest have discussed actual issues of power sector. |
|
May 23, 2011 |
Rosseti North-West |
|
IDGC North-West is among the winners of the contest "Best insurer on obligatory pension insurance” in the territory of the Komi Republic |
|
May 23, 2011 |
Rosseti North-West |
|
IDGC North-West participates in providing electricity to the largest investment project with the price around 186 million euros |
|
May 23, 2011 |
Rosseti North-West |
|
MRSC North-West 24 May will hold the meeting with investors |
|
May 20, 2011 |
Rosseti North-West |
|
Arbitration courts satisfy claims of “IDGCNorth-West” in respect of disputes relating to the "last mile". |
|
May 18, 2011 |
Rosseti North-West |
|
Arbitration court in Vologda did not satisfy the appeal of Federal Antimonopoly Service against the branch “IDGC North-West" “Pskovenergo" |
|
May 16, 2011 |
Rosseti North-West |
|
Three employees of IDGC North-West awarded the title of "Honorary Employee of Energy Industry of the Russian Federation" according to the presidential decree |
|
May 16, 2011 |
Rosseti North-West |
|
"Vologdaenergo” will install two new power transformers at substation 110/10 “Iskra” until the end of May 2011 |
|
May 13, 2011 |
Rosseti North-West |
|
Deputy Director General “IDGC North-West” Olga Makarova held a conference- call with analysts |
|
May 13, 2011 |
Rosseti North-West |
|
In the first quarter of 2011 the capital investments of IDGC “North-West” to the grid complex amounted to 610,6 million rubles |
|
May 12, 2011 |
Rosseti North-West |
|
The Arbitration Court has decided to recover 5,1 million rubles from "Arhenergosbyt" for benefit of “IDGC Northwest” |
|
|
|
1 | 2
|
|
|
|