The branch of IDGC North-West Kolenergo fulfilled technological connection of transshipment terminal JSC “Norilskiy Nickel” to the electric networks

The object was connected to the network, due to held in 2009 reconstruction of substation-5.

Transhipment Terminal JSC Norilskiy Nickel in Murmansk is connected to the electrical network of IDGC North-West Kolenergo from 30 December 2010. The total capacity of connection was performed by 2.6 MW, the voltage level - 6 kV.

As noted by the head of a prospecting development and technological connection department of  Kolenergo Sergei Zaborschikov: "The object was connected to the network, due to held in 2009 reconstruction of substation-5 with the replacement of the transformer T-2 to the more powerful - 63 MVA, thereby creating conditions for connection new consumers. "

The complex reconstruction of substation-5 (110/35/6 kV) has become the largest investment projects of Kolenergo last year. Capital investments totaled 80 million rubles.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z



Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer