print version 

Find company
Home About the ProjectContact usFor the Clients
Enter code or ISIN
 
alpha / industry search

Issuers' Corner
Press Releases
Annual Reports Library

Financial Statements
SEC & FFMS Filings
Corporate Presentations
GM Materials
Issues Documents
Corporate Governance Materials
Russian Company Guide
Company Profiles
Corporate Calendar
Markets Corner
Consensus Estimates
Media Corner
News Line


Get updates



Home  Issuers' Corner  Press Releases  Novolipetsk Steel REGISTER LOG IN

Press Releases > Novolipetsk Steel  all about the company

company search
all press releases
all Novolipetsk Steel press releases

Novolipetsk Steel

April 11, 2008

NLMK upgrades steel-making facilities

Novolipetsk Steel (NLMK) has refurbished and commissioned a Concasting Machine (CCM-4) with a slab capacity of 2 million tonnes per year at its main production site in Lipetsk. The upgrade will ensure better slab surface quality for rolling into flat products.

During the CCM upgrade, newly designed roll sections were installed for the first time in Russia, ensuring a more regular feed of water to cool down the slabs. This will allow a 20-30% increase in the speed of slab treatment and maintain high quality. The curvilinear two-strand machine can cast steel at a speed of up to 1.6 m/min into concast slabs.  These slabs are 200-260 mm thick, 800-1,850 mm wide and 4,500-11,500 mm long.

The project is worth RUR250 million and has been implemented in cooperation with Siemens VAI as part of the 2nd stage of NLMK’s Technical Upgrade Programme. The project will allow NLMK to fully satisfy increased quality requirements from its global customers.

For reference:
The key objectives of the 2nd phase of the Technical Upgrade Programme for 2007 - 2011 include:

- increase crude steel output from 9 to 12.4 million t per year.

- further increase self-sufficiency in key raw materials.

- increase finished rolled flats output from 5 to 9.5 million tonnes per year due to the enhancement and upgrade of NLMK’s existing rolling facilities and the acquisition of new rolling assets. 

Total investment capex into the 2nd phase of NLMK’s Technical Upgrade Programme for 2007-2011 will exceed USD4 billion

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z


Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer