Home  Issuers' Corner  Press Releases
CLOSE

Press Releases

company search
all press releases
all Rosseti North-West press releases

Rosseti North-West

February 2, 2011

Repair Program-2011 of the branch of IDGC North-West "Vologdaenergo” approved in the amount of 317 million rubles

Particular attention in the current year Company will pay to the clearing of firebreaks.

“Vologdaenergo” approved the repair program for 2011 in the amount of 317 million rubles. Particular attention in the current year Company will pay to the  clearing of firebreaks. It is planned to clear 2061 hectares along the lines of power transmission (voltage class 110/35/10 kV).

As part of measures to repair the power grid equipment of «Vologdaenergo”, the specialists will perform repair work at 24 substations 110-35 kV and 266 complete transformer substations. Also will be repaired 96 transformers 10-0,4 kV and a power transformer of 110 kV.

In addition, in 2011 is scheduled the maintenance of battery at a substation 110/35/10 kV “Gryazovets”

Under the plan of the repair program in 2011, the company will repair 338 km of overhead transmission lines 110 kV, 320 km of transmission lines 35 kV, 2064 km of overhead line 10 kV and 418 km transmission line 0,4 kV.

In addition to major works, “Vologdaenergo” will also carry out repairs of administrative and industrial buildings, vehicles and special equipment.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z



Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer