The major direction of the repair activity of "Pskovenergo" will be clearing of the rides along overhead power lines.
In 2011, " Pskovenergo" will send 280 million rubles on the implementation of the repair program The major direction of the repair activity of "Pskovenergo" will be clearing of the rides along overhead power lines. Its necessity is dictated by the fact that much of the power line routes in the Pskov region runs along the forest zone. The trees can cause the short circuits and failures of consumers power supply.
In the five production departments of "Pskovenergo", in 2011, will be renovated 22 substations of 110 - 35 kV, 421 transformer substations 10 / 0, 4 kV. Also it is planned to repair about 1438 km of power lines of different voltage classes, with the replacement, in case of necessity, of separate elements of power transmission lines - isolation,wires and poles.
|