Within the framework of its investment program, in the fourth quarter of this year Mordovenergo, a branch of IDGC of Volga, PJSC (a member of Rosseti Group of Companies), continues construction of Drakino 110/10 kV substation in the Kovylkinsky district of the Republic of Mordovia.
The works are carried out under a public contract on technological connection, which involves construction of a substation with the capacity of 2x6.3 MVA as well as construction of two branches of the 10 kV overhead line to the newly constructed Drakino 110/10 kV substation. In November, as part of the investment program implementation, 6–10 kV oil circuit breakers were replaced with vacuum switches in the following substations: Rabochaya 110/10 kV, Smolnaya 110/10 kV, Teplichnaya 110/10 kV, Zavodskaya 110/6 kV, Romodanovo 110/35/10 kV, Ardatov 110/35/10 kV, Chamzinka 35/10 kV, Vostochnaya 110/6 kV, I-615 110/10 kV.
Construction of all facilities provided for by the investment program of Mordovenergo is to be completed by the end of 2017.
|