The aerial power transmission line of 10 and 0,4 kV voltage is reconstructed in the village Novo-Yakupovo of Abdulinsky district. The works are performed within the frame of the investment program fulfillment of the branch of “IDGC of Volga”, JSC – “Orenburgenergo” in 2009. At the moment 60 new supports are installed in Abdulinsky distribution zone of the Northern Power Grids. It is also planned to install 197 supports and hang approximately 5 km of the insulated wire. Power energy specialist will spent over 8 million rubles to re-equip the power energy grids of this district. New power energy grids will provide qualitative electric energy supply of the agricultural consumers and residential complex of the settlement. The planned replacement of the out-dated power grid equipment all over Orenburg Region is the basis of the engineering policy of the branch of “IDGC of Volga”, JSC – “Orenburgenergo”.
|