For this purpose "Pskovenergo" will spend 46.3 million rubles (including VAT). Until the end of September 2011, a branch of “IDGC North-West" "Pskovenergo" will reconstruct the four substations110 kV - ¹ 116 "Dno" ,¹ 309 "Pustoshka" ¹ 148 "Pytalovo" and ¹ 133 "Idritsa".
For this purpose "Pskovenergo" will spend 46.3 million rubles (including VAT).
Reconstruction will be carried out by the company "Pskovenergoremont." The contractor has been identified on the basis of open competition, which was held on an electronic trading platform of Holding IDGC.
All of these substations were built in the 60's and 70's of last century. Switching equipment, which was to be reconstructed, no longer meets modern standards and requirements of new technological systems. 110 kV circuit breakers are more compact, reliable in operation and require minimal maintenance.
|