June 28, 2011

"Vologdaenergo" started the assembling of indoor distribution device 10 kV 35/10 kV at the substation "Ida" in Babushkinskiy district (Vologda region)

Entering of fixed assets is planned for the fourth quarter of 2011.

Branch of JSC "IDGC North-West" "Vologdaenergo" carries out the reconstruction of 35/10 kV substation "Ida" in Babushkinskiy district (Vologda region). During the reconstruction were installed the metal fences, the oil collector, was made the foundation  for floodlight tower of power lines.

Currently on the site, the contractor performs the installation of the indoor distribution system 10 kV. In addition, at the new substation is carrying out the assembling of portals of outdoor distributing device 35 kV. At the substation already  placed 85% of main power equipment.

Entering of fixed assets is planned for the fourth quarter of 2011. The cost of the investment project will be about 30 million rubles.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z



Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer