Financing of the investment project will be about 22 million rubles.
Branch of JSC "IDGC North-West" "Vologdaenergo" began the reconstruction of 35/10 kV substation "Ustie--Kubenskoe". The project realization is due to increase in requests for technical connection.
As part of the project was provided the replacement of the main equipment, including power transformers to the new - TOTRc-6300/35/10 with devices of automatically adjust the voltage levels under load. Currently on site are conducted preparatory work and delivery of necessary materials.
The project "Reconstruction of substation «Ustie--Kubenskoe" 35/10kV is necessary to increase the substation transformer capacity and increase the efficiency of electricity supply. This also will increase the reliability of electricity supply. Financing of the investment project will be about 22 million rubles.
|