July 26, 2016

LUKOIL commissions Phase I power supply at Usinskoye field, Komi

PJSC LUKOIL commissioned Phase I of the auxiliary power supply plant in the Republic of Komi.
The 100 MW power plant is designed to satisfy the growing need in power at the Denisovsky license area and will increase utilization of associated petroleum gas.
The project, developed and implemented by PJSC LUKOIL’s wholly owned subsidiary, LUKOIL-Engineering LLC, was completed in only 14 months thanks to domestically produced basic equipment and use of innovative technologies at all stages of construction.
Commissioning of Phase II of the power plant will provide heat for the purposes of the Usinskoye field operation and allow better efficiency of production at permo-carboniferous deposits.


Press Centre  PJSC "LUKOIL"
Phone.:+7 (495) 627-16-77
E-mail: media@lukoil.com

https://www.lukoil.com
https://www.facebook.com/Lukoil.en
https://twitter.com/lukoilengl

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z



Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer