LenEnergo increased the number of fulfilled technological connection agreements by 25% in the first half of 2014

In the first half of 2014, ROSSETI's subsidiary LenEnergo has increased the number of fulfilled technological connection agreements by 25%, up to 3,877, as compared with 2013. For the entire Leningrad Oblast, this indicator rose to 38%, up to 3,155 agreements.

The energy volume for these contracts increased by 11.8% and amounted to 129.9 MW. A growth of 52.1% has been registered for St. Petersburg, up to 50.5 MW.

During the first half of 2014, LenEnergo concluded a total of 7,083 technological connection agreements for a total of 236 MW of power. In St. Petersburg, the company concluded 1,821 agreements for a total of 113 MW, and 5,262 agreements in the Leningrad Oblast for 123 MW.

Over the first six months of 2014, LenEnergo has accepted 12,449 applications for technological connection, which is 11.6% higher than the same time last year. This includes 3,194 applications in St. Petersburg and 9,255 in the Leningrad Oblast. Meanwhile, the total requested power in the region increased by 9.8% and amounted to 713.6 MW.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z



Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer