May 25, 2020

Orenburg production division of Orenburgenergo will repair electric grids

The teams of the Orenburg Production Office (PO) of the Orenburgenergo branch of Rosseti Volga (a brand of IDGC of Volga, PJSC) repair electrical equipment in Orenburg and its suburbs.

The repair campaign began in March, and with the onset of warm weather, the number of facilities operated by power engineers increased several times. Until October, they will have to repair 816 transformer substations, more than 400 km of power lines. Power engineers will replace 199 wooden supports with reinforced concrete supports, about 10 km of bare wire with insulated wire. The amount of funding will be about 59 million rubles.

This year, the repair plan included power grids along the streets of Zheleznodorozhnaya, Kazakovskaya, Konduktorskaya, Tereshkovoy, Omskaya, Kirova, 25th line, 83rd line, 4th Paromnaya, Kashirina, Proletarskaya, Ural embankment, Potekhina, Sakmara embankment, Volochaevskaya, Velikanova, Amurskaya, lanes Ardatovsky, Kovalenko, Dobychny.

The work is also planned in the Orenburg region: in the villages of Gorny, Arkhangelovka, Chkalov, Svetlogorka, Prigorodny, Podgorodnaya Pokrovka, Bylynny, Mirny Put, Chebenki, and the village of Nikolskoye.

“All types of work with the arrangement of the objects of brigades and equipment are planned for a month. All the preparations for the autumn-winter period, we must complete before September 30. In conditions of a difficult epidemiological situation, all repair personnel are provided with the necessary protection and hygiene equipment, and the health status of workers is constantly monitored,” said Vadim Shaldin, Director of the Orenburgskoye PO.

Power engineers warn: during repairs, the supply of electricity to households, enterprises and organizations will be limited. This is a necessary measure: electricians are located on power lines and in transformer substations, for their safety, objects are de-energized. By evening, electricity will be restored.

Three days before the work, dispatchers will warn the management companies and housing cooperatives responsible for the electrical facilities of enterprises and organizations about blackouts. Information on planned outages in Orenburg and suburban settlements is also published on: – the city administration website https://orenburg.ru/ – the portal https://www.orenday.ru/ – on the ORT Planet TV channel at 19.35.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z



Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer