In October, Komienergo plans to complete expansion of forest corridors of eight 110 kV overhead transmission lines. Currently works are in progress on overhead lines “Mikun-Syktyvkar” and “Mikun-Edva”. By October 20, the Company intends to put into regular scheduled operation “Zapadnaya” 110/10 kV substation in Syktyvkar. “Sokolovka-Pazhga” 110 kV line, the first stage of Komienergo large-scale investment project “Syktyvkar Timber Processing Complex CHP – Vizinga substation 110 kV overhead line”, is to be delivered into operation in October. “Sokolovka-Pazhga” line will be the first double section constructed in the south of the republic.
|