In the Murmansk region completed the reconstruction of substation-64 (110/35/6 kV) of JSC "IDGC North-West" "Kolenergo". The reconstruction is made with the replacement of 25 MVA transformer with a more powerful - 40 MVA. These measures have increased the total capacity of 15 MW substation, increase the reliability of electricity supply of the Eastern district of Murmansk, provided an opportunity to connect new consumers. The total project cost amounted to about 7 million rubles
|