Specialists of Orenburgenergo, a branch of IDGC of Volga, PJSC (a member of Rosseti Group of Companies), conduct construction of 110 kV overhead line (OL) along with reconstruction of NPS substation (SS) within the investment project.
The project is divided in two phases: reconstruction of SS NPS and construction of the OL. Two additional cells will be installed for power supply to Chkalovskaya SS after its transfer to 110 kV voltage. Also 10 disconnecting switches and their control cabinets, and bus and linear portals will be mounted.
The second phase of the project — the construction of 110 kV double-circuit OL and its connection to the installed cells — power workers will begin next year. The complex of measures will greatly enhance the quality of power supply to consumers of the northern regions of the Orenburg region — residents and oil companies.
|