print version 

Find company
Home About the ProjectContact usFor the Clients
Enter code or ISIN
 
alpha / industry search

Issuers' Corner
Press Releases
Annual Reports Library

Financial Statements
SEC & FFMS Filings
Corporate Presentations
GM Materials
Issues Documents
Corporate Governance Materials
Russian Company Guide
Company Profiles
Corporate Calendar
Markets Corner
Consensus Estimates
Media Corner
News Line


Get updates



Home  Issuers' Corner  Press Releases REGISTER LOG IN

Press Releases

company search
all press releases
all Rosseti Volga press releases

Rosseti Volga

July 15, 2021

"Mordovenergo": the repair program is being carried out in accordance with the schedule

The specialists of the Mordovenergo branch of RossetiVolga, PJSC are actively working on the implementation of the maintenance and repair program.

In July 2021, six 110 kV substations are being repaired. The largest among substations are:  110 kV Babeevo , 110 kV Staroe Shaigovo , 110 kV Kaz  Maidan". The list of electrical equipment to be repaired in July also includes five  35 kV substations. Of these, the largest amount of work will be carried out at the foillowing  35 kV substations: "Purkaevo",  "Bulgakovo", "Kalinovka". To improve the reliability and safety of power supply to consumers, 2.1 km of 110 kV lines will be repaired: 110 kV Ruzaevka-Yugo – Zapadnaya overhead line, 110 kV Umys-Zhurlovka overhead line. Repairs were carried out at 118 transformer substations.

Intensive work is being carried out to clear the routes of overhead power lines. The works are planned on an area of almost 225.5 hectares. Specialists use a mechanized and manual method of removing tree and shrub vegetation.

Repair work is the most important part of the package of measures to prepare the branch's electric grid facilities for the autumn-winter period of 2021/2022. They are carried out to improve the reliability, quality and safety of electricity supply to consumers, industrial and agricultural enterprises of the region. In total, 29.25 million rubles will be allocated for the implementation of the repair program in July.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z


Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer