In 2011, IDGC of the North-West technological connection CAPEX made 2087 mln RUR (126% of the plan), including those on preferential consumer connection 1,176 mln RUR In 2011, IDGC of the North-West, JSC incurred CAPEX in an amount of 5170 mln RUR which is 103% of the plan (5037 mln RUR). The assimilation volume increase is due to growth of consumer technological connection costs. In 2011, IDGC of the North-West technological connection CAPEX made 2087 mln RUR (126% of the plan), including those on preferential consumer connection 1,176 mln RUR (145% of the plan). Over-fulfillment of assimilation volumes with preferential categories consumers technological connection is ensured by the company through saving following the results of tenders and due to partial switchover to performance of works using the company's own resources.
|