The electric grid 110 kilovolt «Pleshanovo – Kalikino» in the extent of 47,3 km which has connected the western part of the Orenburg region with central and northern, passes on Krasnogvardejsky and Aleksandrovsky areas of the Orenburg region. Now there is a following stage of building of power knot - power of the Western electric networks "Orenburgenergo" carry out reconstruction of substation 110/35/10 ę "Pleshanovsky". The most labour-consuming work is finished. In 2009 it is necessary to instal and adjustment of the established equipment to lay new cable channels and cables. Works is planned to finish in III quarter 2009 year.
|