In the first quarter of this year, in the framework of the investment program of the branch of IDGC of Volga, PJSC (included in the Rosseti group) - Mordovenergo, for 2019, utility connection of several facilities is planned.
Thus, it is planned to complete the construction and commissioning of the transmission line VLZ-10 kV with a length of 7 km at the request of OOO «Mordovskij plemennoj centr». Within the framework of the same project, the switchgear will be reconstructed at the substation 110/10 kV Substation "Russkaya Payevka".
Modernization of the power facility and construction of the line will ensure reliable power supply to the pig-breeding complex for 4,800 breeding pigs located in the village of Zasechnaya Sloboda, Insarsky District of the Republic of Mordovia. In the first quarter it is planned to conduct tender procedures for the selection of contracting organizations for the implementation of investment projects (reconstruction of distribution grids facilities, remote control and technological communication) planned for 2019.
|