Specialists of Saratov Distribution Grids, a branch of IDGC of Volga, PJSC (a member of Rosseti Group of Companies), have completed the scheduled repair of 110/10 kV Pishchevaya substation in the Leninskiy District of Saratov. The works were carried out as part of the 2016 repair program aimed at preparation for the 2016–2017 autumn and winter period. Power engineers performed capital repair of 110 and 10 kV disconnecting switches, 110 kV separators, 110 kV short-circuit switches, and 10 kV switches. The repairs covered 110/10 kV power transformers, 110 kV dischargers, 10 kV busbar sections and busbar bridges, and 10 kV overvoltage limiters. Metal structures of equipment were painted. The scheduled repair of 110/10 kV Pishchevaya substation will make it possible to increase reliability of electric power supply to consumers during the forthcoming 2016–2017 autumn and winter period and to extend the life cycle of the equipment in operation.
|